7. Construction

That you know how what you draw actually gets built — sequence, temporary conditions, tolerance, access, plant — and that you have contributed to that process rather than watched it.

Who this is for:Candidates at any stage ·Mentors

Minimum standard: Experience for Incorporated-Member, Experience for Chartered Member.

Core Objective 7 — what IStructE says

Institution of Structural Engineers

  • This objective is intended to demonstrate a candidate's experience of the practical process to convert design work into completed structures and should demonstrate that they are able to contribute to this in a meaningful way.
  • Minimum standard, Incorporated-Member: E — Experience. The subject should be performed independently or under supervision.
  • Minimum standard, Chartered Member: E — Experience. The subject should be performed independently or under supervision.

From IPD Guidance — Chartered Member, Institution of Structural Engineers.

What strong and weak evidence look like

Worth doing

  • A design change you made because of how it would be built.
  • A temporary condition you identified that governed the permanent design.
  • A site problem you were called to and resolved, with what you decided.
  • A construction sequence you thought through, including the stage that was most vulnerable.
  • Evidence of tolerance, setting out or fit being designed for rather than discovered.

Avoid

  • Site visits with photographs, and no decision attached.
  • "I attended site meetings."
  • A design with no evidence that anyone considered how it would be erected.
  • Treating buildability as the contractor's problem.

Portfolio items that tend to work here

4 items · saved in this browser only

Suggestions, not a required list. What matters is that the item is yours, that it is annotated, and that it demonstrates the standard rather than the subject.

Questions to ask yourself

  1. What is the worst stage during construction?

    The temporary condition governs far more often than candidates expect.

  2. What did I change because of how it would be built?

    That change is the evidence. Awareness of buildability is not.

  3. Have I been on site for my own design?

    It is the single most common gap in an otherwise strong design-office portfolio.

The same objective, in different kinds of work

Illustrative. The objectives are written to be met in a range of ways by anyone practising as a structural engineer.
SettingWhat the evidence tends to look like
DesignerChanging a detail so it could be built without working at height, and recording what remained.
Site engineerSequencing a pour or a lift, and holding the line when the programme pushed back.
Temporary worksDesigning or checking a propping scheme, and setting what had to be verified before load was applied.

Illustrative. The objectives are written to be met in a range of ways by anyone practising as a structural engineer.

How reviewers tend to approach this objective

There is a bank of original practice questions in the interview question bank, filterable by objective and by grade.