2. Management and Leadership

That you can plan and run work, use people and resources well, and help others get better at what they do.

Who this is for:Candidates at any stage ·Mentors

That you can plan and run work, use people and resources well, and help others get better at what they do.

Attribute area 2 — the official statements

Institution of Civil Engineers

  • Plan the work and resources needed to enable effective implementation of engineering tasks and projects
  • Manage the planning and organisation of tasks and resources — at Chartered level: and manage (organise, direct and control), programme or schedule, tasks and resources
  • Manage teams or technical specialisms — at Chartered level: and lead or influence teams / technical specialisms, understanding the limits of their skills and knowledge
  • Assist others to meet changing technical and managerial needs — at Chartered level: and develop others to meet changing technical and managerial needs
  • Manage quality processes and contribute to quality improvements — at Chartered level: and demonstrate continuous quality improvement and promote best practice

From Incorporated and Chartered Professional Review Guidance, Institution of Civil Engineers.

What this area is really asking

That you can plan and run work, use people and resources well, and help others get better at what they do.

Where Chartered differs

The IEng statements are about managing work well. The CEng extensions add direction and development: leading or influencing rather than managing within a set structure, developing people rather than assisting them, promoting best practice rather than contributing to it. Note the word influence. Leading a team you have no line authority over is squarely within this, and for many engineers it is the more honest description of what they actually do.

What strong and weak evidence look like

Worth doing

  • A programme you built, what you got wrong in it, and how you recovered.
  • A resourcing decision with a real constraint behind it — someone you could not have, a skill you did not have.
  • A time you changed a colleague's approach by persuasion, and what argument actually worked.
  • Concrete development of someone else: what they could not do before, what they could do after, and your part in that.
  • A quality process you changed because it was not catching what it was meant to catch.

Avoid

  • A job title offered as evidence of leadership.
  • "I managed a team of twelve" with nothing about what managing them involved.
  • Attending meetings, described as chairing them.
  • Quality described as following the QA system, with no example of it failing or improving.
  • Long lists of responsibilities with no decision in them.

Fictional example

Leading without authority

Fictional example — highways, consultant, no line reports

Weaker

I worked closely with the drainage and geotechnical teams to coordinate the design and ensure the programme was met.

Stronger

Drainage and geotechnics were producing incompatible assumptions about the groundwater level, and neither team would move because each had a different source. I had no authority over either. I got the two leads into a room with the borehole logs and the drainage model on the same screen, and it took twenty minutes to establish that one had used the standing level at drilling and the other the long-term recovered level. We agreed the recovered level, I wrote it into the design assumptions register, and I got both leads to sign it. It removed a rework that would have cost about three weeks.

Why — There is a specific problem, a specific reason nobody could just be told what to do, an action the candidate took, and a consequence. It also shows an understanding that the fix was a governance one — writing it into the register — rather than just a conversation.

Questions to ask yourself

  1. When did I have to choose between two things I could not both do?

    Management evidence is made of trade-offs. Where there was no constraint there was no management decision.

  2. Who did I have to bring with me, and how?

    Influence without authority is often the strongest CEng leadership evidence available to a junior-titled engineer.

  3. What did I delegate, and how did I assure myself it was done properly?

    Delegation with retained accountability is the pattern reviewers look for.

  4. Who is better at their job because of me?

    The CEng extension is 'develop others'. A specific person and a specific improvement answer it; a mentoring policy does not.

The same area, in different kinds of work

Illustrative. The area is generic by design — ICE says the attributes can be achieved in a range of ways by anyone working as a civil or infrastructure engineer.
SettingWhat the evidence tends to look like
Contractor, siteSequencing a possession, deciding what to drop when the weather went against you, and holding the quality line under programme pressure.
Consultant, project managementRestructuring a delivery team when a discipline fell behind, and being straight with the client about the consequence.
Client organisationDirecting a supply chain towards an outcome rather than a specification, and holding designers to account without designing for them.
Asset managementPrioritising an intervention programme against a fixed budget and defending what you chose not to do.

Illustrative. The area is generic by design — ICE says the attributes can be achieved in a range of ways by anyone working as a civil or infrastructure engineer.

Fictional example

Developing someone, rather than helping them

Fictional example — contractor, section engineer

Weaker

I mentored a graduate engineer and provided support and guidance to help them develop.

Stronger

The graduate on my section could set out but could not read a temporary works design well enough to know when what was built did not match it. Rather than checking it for him, I took him through the propping design for the headwall — load path, what each member was doing, what would happen if the raking shore was 200 mm off. Then I had him do the pre-pour check himself and talk me through it. Two weeks later he stopped a lift because the toe restraint had not been installed. He would not have spotted it in March.

Why — The CEng extension is 'develop others'. This names what the person could not do, what the candidate did about it, and the evidence that it worked. Compare the weaker version, which could have been written by anyone about anyone.

An evidence-planning exercise

4 items · saved in this browser only

Written for a notebook rather than a submission. Anything you cannot answer is a development action, not a writing problem.

How interviewers tend to approach this area

There is a large bank of original practice questions in the question bank, filterable by area and by level.